Server maintenance is scheduled for Saturday, December 21st between 6am-10am CST.

During that time, parts of our website will be affected until maintenance is completed. Thank you for your patience.

Search
Filters
Close

Use GIVING24 at checkout to save 20% on eCourses and books (some exclusions apply)!

02333 ELECTROCHEMICAL NOISE MEASUREMENTS IN A 500 MW STEAM TURBINE TO MAXIMISE LIFETIME UNDER CHANGING OPERATIONAL DEMANDS.

Product Number: 51300-02333-SG
ISBN: 02333 2002 CP
Author: G.J. Bignold and G.P. Quirk
Industry: Energy Generation
$0.00
$20.00
$20.00
Steam turbine blade and disc failures have occurred from time to time throughout the world. Although they are rare events, the implications for safety, for repair costs and for loss of availability are severe. Current operational and maintenance practices for any particular turbine design may be based on many years of satisfactory service. However, recent deregulation of the power industry in the UK and forthcoming deregulation in the USA may have an effect on operational and reliability issues, as changing operational demands are placed upon power generators through economic forces. In the UK in the 1990s with deregulation and privatization of power generation, the introduction of high efficiency gas fired stations has transformed the profile of the industry. The nuclear stations, which can only operate safely under base load conditions, were protected by government regulation (the socalled “nuclear levy”). These gas fired and nuclear plants, together with those coal-fired stations that have been fitted with flue gas desulfurization (FGD) systems, accounted for the majority of base load supply. The remaining coal-fired stations were, therefore, forced towards operating for peak demand rather than base load. They have had to develop operating procedures that enable them to provide power flexibly and economically with rapid response to variable demand. One of these procedures covers running up the unit to stable conditions before power is produced. This paper gives an account of the research carried out to confirm the risks of turbine damage, which was essentially due to corrosion during the start-up sequence. The paper illustrates the research that was carried out over 7 months using on-line corrosion monitoring with the electrochemical noise technique. Probes were installed directly within the low pressure (LP) section of an operating 500 MW turbine to gather data that would demonstrate the cause of pitting corrosion at the turbine blade root. This pitting had been found to be the primary factor in the onset of stress corrosion cracking (SCC), which eventually caused the failure of a turbine blade with very serious consequences for the unit.
Steam turbine blade and disc failures have occurred from time to time throughout the world. Although they are rare events, the implications for safety, for repair costs and for loss of availability are severe. Current operational and maintenance practices for any particular turbine design may be based on many years of satisfactory service. However, recent deregulation of the power industry in the UK and forthcoming deregulation in the USA may have an effect on operational and reliability issues, as changing operational demands are placed upon power generators through economic forces. In the UK in the 1990s with deregulation and privatization of power generation, the introduction of high efficiency gas fired stations has transformed the profile of the industry. The nuclear stations, which can only operate safely under base load conditions, were protected by government regulation (the socalled “nuclear levy”). These gas fired and nuclear plants, together with those coal-fired stations that have been fitted with flue gas desulfurization (FGD) systems, accounted for the majority of base load supply. The remaining coal-fired stations were, therefore, forced towards operating for peak demand rather than base load. They have had to develop operating procedures that enable them to provide power flexibly and economically with rapid response to variable demand. One of these procedures covers running up the unit to stable conditions before power is produced. This paper gives an account of the research carried out to confirm the risks of turbine damage, which was essentially due to corrosion during the start-up sequence. The paper illustrates the research that was carried out over 7 months using on-line corrosion monitoring with the electrochemical noise technique. Probes were installed directly within the low pressure (LP) section of an operating 500 MW turbine to gather data that would demonstrate the cause of pitting corrosion at the turbine blade root. This pitting had been found to be the primary factor in the onset of stress corrosion cracking (SCC), which eventually caused the failure of a turbine blade with very serious consequences for the unit.
PRICE BREAKS - The more you buy, the more you save
Quantity
1+
5+
Price
$20.00
$20.00
Product tags
Also Purchased
Picture for 00628 CORROSION AND EROSION-CORROSION BEHAVIOR
Available for download

00628 CORROSION AND EROSION-CORROSION BEHAVIOR OF A Co-BASED ALLOY AND A Ni-CONTAINING AUSTENITIC CAST IRON

Product Number: 51300-00628-SG
ISBN: 00628 2000 CP
Author: A. Neville, H. Xu and M. Reyes
$20.00
Picture for 01202 ELECTROCHEMICAL MONITORING IN CORROSION
Available for download
Picture for 00743 COPPER GROUNDING SYSTEMS HAVE A NEGATIVE
Available for download

00743 COPPER GROUNDING SYSTEMS HAVE A NEGATIVE EFFECT ON CATHODIC PROTECTION IN PRODUCTION FACILITIES

Product Number: 51300-00743-SG
ISBN: 00743 2000 CP
Author: Earl L. Kirkpatrick, P.E., Mohammad Shamim
$20.00